Forever Electromechanical Equipment Factory is a high-tech manufacturer specializing in the research and development of steel pipe induction hardening and tempering furnace in China. We have always been committed to producing high-quality products at a lower cost. Our Forever steel pipe heat treatment furnace has simple and efficient operation, making your work efficiency higher and production costs lower. Forever Electromechanical has been engaged in the field of induction heating and heat treatment for many years, and has produced multiple sets of induction heating complete sets of equipment with mature technology and rich experience.
Forever Electromechanical Equipment Factory can configure additional equipment according to user requirements, including automatic feeding machine, discharging machine, discharging sorter, and closed cooling water circulation system. Provide users with professional and efficient induction heating solutions for free; We have strong pre-sales and after-sales services to ensure the quality and normal operation of our customers’ steel pipe quenching and tempering furnaces.
The specific process of Forever steel pipe heat treatment furnace is:
1. Straightening: After manually placing the steel pipe on the feeding platform and leveling it, it is sent to the parallel roller conveyor in a step-by-step manner by the feeding machine, and then enters the pre heat treatment roller straightening machine for straightening. After straightening, it is sent to the mechanical traction machine in front of the sensor through the parallel roller conveyor;
2. Induction hardening: Steel pipes are transported by a traction machine to a semiconductor frequency converter for induction heating in the induction heating quenching system. The equipment is controlled by an output sensor cabinet and an infrared thermometer, and automatically controls the temperature of the steel pipes through preheating, temperature measurement, temperature rise, and temperature measurement. When the quenching temperature is reached, the steel pipes enter the cooling system for quenching. They are then transported by a mechanical traction device to a roller conveyor and sent to the storage and loading platform. At the same time, non-conforming quenching products are separated to complete the quenching process,
3. Tempering: After quenching, the steel pipe is mechanically pulled into the feeding platform and fed into the parallel roller conveyor in a step-by-step manner. It is then fed into the mechanical traction machine in front of the intermediate frequency power supply sensor, where the steel pipe moves steadily and the steel rod is fed into the sensor for tempering. After temperature measurement, it enters the tempering insulation box for insulation delay. After tempering, it is hot straightened and then fed into the parallel roller conveyor;
4. Cooling bridge straightening: Steel pipes enter the cooling bed for natural rolling cooling, and after cooling, they are sent to the straightening machine for straightening and demagnetization treatment
5. Material inspection and storage;
Overseas manager: Tom Wang
Email:tom@foreverfurnace.com
Phone: 0086-13303078975(whatsapp, wechat,line)
Specialist of bar heat treatment furnace in China; Glad to be your business partner in induction heating field.
Post time: 10-31-2024